Construction of Power line from Mine Site to Town Sub Station Project
Name of Principal Rio Tinto Iron Ore
Engineer  
Project Construction of Power line from Mine Site to Town Sub Station Project
Location Paraburdoo Mine / Town Site
Southern Cross Project Scope Construction of approximately 12km’s of 33kV Power line from the Mine Site to Paraburdoo Town Sub Station East. The line is exceptionally large conductor as it will not only act as a secondary Town Feeder it will also feed the proposed Turee Iron Ore Mine
Time 2008
Southern Cross Value Add  

 

 

Subscribe